Basket case is a medium sized company, established in 1992, with a turn over of AUD 85 million per annum. They are market leaders in manufacturing cane and plastic baskets which is sold to retail shops and some large retail chains. They also have an online shop, catering to the end user directly.
A study was conducted to assess their current business operations and their capability to adapt to the future growth in the market. The results recommended certain factors to be in place for improving the company's performance in the market. On seeking professional consultation with BlueSky - an ERP solution provider, it was advised to implement an Information System. Also suggestions were made to re-engineer many of the company's business processes by developing a Business and IT strategy plan. The core competitive business strategy plan were,
§ Increase their market share by targeting major retail outlets, such as major supermarket and hardware chains. Emphasis in this sector is to be on price competitiveness.
§ Maintain its existing customer base among small-medium retail outlets. Emphasis in this sector is to be on quality product combined with superior service.
The plan is to make phased changes within the Basket Case Company to achieve the competitive strategy,
§ A new product range with brand line differentiation. This is needed to service the two different markets - large chains and small-medium enterprises (SMEs).
§ Within twelve months, Basket Case should embark on a programme of investment in state-of-the-art manufacturing machinery. The aim of the programme is to significantly increase the productivity of the manufacturing process and to reduce costs.
§ Demands for electronic supply chain management from the large chains require that Basket Case abandon its manual internal processes in favor of electronic-based management.
§ Requirements for superior service in the SME sector also require capable electronic management systems.
The major points that were discussed in the IT strategy plan were:
§ Basket Case should immediately update its internal processes.
§ A phased out implementation of Blue Sky ERP package department wise.
§ Careful attention should be paid to re-engineering business processes and to staff development.
Project Charter
The main objective of this project is to implement an ERP solution and upgrade their current infrastructure on an effective time and material basis. The ERP package to be implemented is ‘BlueSky' which needs to be customized to facilitate the smooth migration from existing systems and timely maintenance of the package. An appropriate ICT infrastructure also needs to be put into operation in order to support the proposed information system.
Roles and Responsibilities
List the roles and responsibilities of the stakeholders and senior project team members.
Name | Role | Responsibility |
---|---|---|
GaneshKumar C S | Delivery Manager | Responsible for the delivery of solutions for an agreed portfolio of technologies - this includes strategy, design, development and support,as well as people leadership. |
AshwinKumar Shetty | Project Leader | Draft initial charter and project plan. Coordinate efforts for completing activities in plan. Update plan regularly. Provide regular status reports for all activities related to the project. Work with Project Manager to ensure resource workload is balanced across projects. Serve as the single point of contact for the Team to the project stakeholders. |
Prabhu Manoharan | Onsite Coordinator | Requirements gathering and documentation (functional, technical, stated, implied) - if applicable Scope change management Customer management (customer expectation management, balancing Customer/Team/Organization perspectives) Effective customer feedback / requirement communication to offshore team Ensuring timely finalization of reasonable acceptance criteria and timely sign-offs on project artifacts Onsite technical issue handling (design reviews with client, build integration onsite, diagnosis and reporting of technical issues) |
Prabhu Varadan | Project Manager | Overall responsibility for the project execution as per the Quality Management System Approval of project plans and estimates Approval of technical documents. Providing resources for the project Reporting project status to stakeholders and internal management Review Business continuity plan of the project |
Provide a high level schedule of the project - preferably using a Gantt chart - top one or two levels of sub-task only.
Provide a budgetary estimate for the project. The budget should be a summary but in enough detail to allow intelligent decision making based on the budgetary figures.
Sign-off of all the above stakeholders.
Project Scope Statement
BlueSky has to implement the ERP package in Basket Case and build the infrastructure to maintain the physical systems. The training and post implementation 1 year warranty also falls under the scope.
A scope and Business Plan document was shared with the stake holders at Basket Case and verified. It was verified and validated by the stakeholders and signed off. The proposed project plan and all the documents related to the same are clearly verified and accepted by the project sponsor (The Basket Case) and the project contractor (BlueSky). Any minor changes in the scope of the project which does not affect the project schedule, cost and time can be undertaken on mutual agreement between project sponsor and the delivery manager. Any other changes will be undertaken after a detailed brainstorming between the project stake holders and BlueSky team and captures in the Change Request form.
All the documents (Change Request form) must be signed by the stake holders. Only on consensus from the stake holders the project manager will consider the effect of the scope change and re-evaluate the project with the required changes in the project schedule, resource requirement, costing, human resource requirement, technical changes and project completion time. The final document should be signed by the project sponsor and the project manager before the changes can be implemented.
Work Breakdown Structure
Task Name | Duration | Start | Finish |
Project Kick Off | 1 week | Mon 4/5/2009 | Mon 4/12/2009 |
Review of Business case | |||
Team Meeting | |||
Financial Planning | |||
Distribution of Responsibilities | |||
Infrastructure Planning | 15 days | Mon 4/5/2009 | Tue 19/05/2009 |
Order placement for Hardware | 20 days | Wed 20/5/2009 | Sat 30/5/2009 |
Order Dell Desktops | 3 hrs | ||
Order Dell Laptops | 1.5 hrs | ||
Order all Servers | 3 hrs | ||
Order Printer | 0.5 hrs | ||
Order UPS | 0.5 hrs | ||
Order Modem/Router, Hub | 1 hr | ||
Order Completion | 2 days | ||
Delivery of Hardware | 7 days | ||
Order Placement for Software | 5 days | Thu 01/6/2009 | Sat 20/6/2009 |
Order Oracle software | 1 day | ||
Order Linux | 1 day | ||
Order Windows NT Server | 1 day | ||
Order Microsoft Office | 1 day | ||
Order Internet Package(TPG) | 1 day | ||
Order Completion | 2 days | ||
Delivery of Software | 2 days | ||
Server Room Construction | 2 days | ||
Employ Builder | 1 days | ||
Completion of Server room | 6 days | ||
Cabling | 6 days | Mon 21/6/2009 | Thu 28/6/2009 |
Order cables | 2 hrs | ||
Employ Smith cables Contractor | 5 days | ||
Cabling Accomplished | 5 days | ||
Installation of PC's, Servers | 1 day | Fri 28/6/2009 | Fri 29/6/2009 |
Setting up of LAN and connecting to internet | 1 day | Mon 01/7/2009 | Mon/7/2009 |
Testing network Functionality | 1 day | Tue 02/7/2009 | Tue 02/7/2009 |
Infrastructure Ready | 1 day | Wed 03/7/2009 | Wed 03/7/2009 |
Installation of Software | 7 days | Thu 04/7/2009 | Thu 11/7/2009 |
Server Setup/Installation of OS and software to server | 3 days | ||
Installation of software to desktop/ Laptop | 10 days | ||
Installation Complete | 10 days | ||
Customize BlueSky Package | 90 days | Fri05/7/2009 | Mon 05/10/2009 |
Order BlueSky | 5hrs | ||
BlueSky delivery | 30 days | ||
Accounts Payable | 2 days | ||
Accounts Receivable | 2 days | ||
Bank Interface | 10 days | ||
Cash Book | 20 days | ||
Cost Management | 30 days | ||
Fixed Assets | 30 days | ||
General Ledger | 25 days | ||
Inventory | 20 days | ||
Order Entry | 20 days | ||
Purchase Orders | 10 days | ||
Verification and Validation of BlueSky | 2 weeks | ||
Team Meeting | 10 days | ||
Customization Complete | 60 days | ||
Backing up Existing Data | 30 days | Tue 06/10/2009 | Mon 07/11/2009 |
Data Entry | 20 days | ||
Data Validation | 20 days | ||
Backup Complete | 24 days | ||
System Acceptance testing | 20 days | Tue 08/11/2009 | Thu 28/11/2009 |
Testing Complete | 30 days | ||
Training/Documentation | 10 days | ||
Project Finalization | 10 days | Thu 28/11/2009 | Mon 31/11/2009 |
Team Meeting | 20 days | ||
Board Meeting | 60 hrs | ||
Budget cross check, profit/loss analysis | 1 week | ||
Project Signoff | 4 days | Tue 2/12/2009 | Thu 4/12/2009 |
The delivery manager and the project manager worked together to plan the schedule for the project. The scheduling was done with care taking into mind threshold period for the project.
If a change request is issued by the external contractor, the Project Manager will undertake Impact Assessment. The impact assessment will comprehensively set out the details of the proposed change including: the details (and technical specifications of the change); the impact that the change will have on the performance and achievement. The Impact Assessment also includes a plan that details how the changes are implemented and a new timetable and budget estimate.
Human Resource Requirement
Resource Name | Units |
Project Manager | 1 |
Software Consultant | 1 |
Software Engineer | 3 |
Desktop Computer Support Personal | 2 |
Network Engineer | 2 |
Technical Writer | 1 |
Hardware Consultant | 1 |
Trainer | 1 |
Software Team Leader | 1 |
Hardware Team Lead | 1 |
Data Entry Operator | 1 |
Training Requirements
§ Quality Management Systems skills
§ Technical skills
§ Non-Technical Skills.
If there is a gap in the existing vs. required skills, then indicate how the gap will be closed, and when. Training modes can be of the following,
§ J - On the job
§ C - Class room/Workshop
§ M - Training/Orientation through Mail
§ S - Structured Self Learning
S. No. | Role | Training required | Training Mode |
1. | Delivery Manager | PMM Certified, Internal process certified | S |
2. | Project Manager | PMM Certified, Internal process certified | J, S |
3. | Project Lead | Internal process certified, Technical Certifications | J, S |
4. | Onsite Coordinator | Internal process certified, Technical Certifications | J, M, S |
5. | Quality Analyst | Internal process certified, Technical Certifications, SCM certification | J, S |
6. | Developer | Internal process certified, Technical Certifications | J, C, S |
7. | Tester | Internal process certified, Technical Certifications | J, C, S |
Project Communication Management Plan
Communication Matrix
§ The Project Manager will brief the overall progress to the sponsor on a weekly basis. This will be in the form of a Weekly Progress Report, including completed tasks, upcoming tasks and expenses incurred.
§ Any noticeable change in the project will be informed to the sponsor by the Project Manager. The changes will be documented in the Project Status Report.
§ Any change request from the Sponsor is done through the Change Request Form to the Project Manager.
§ Any communication between the stake holders resulting in the Project change or regarding the project should be done through e-mails. It also necessary to document the change proposed and file a hard copy. Stake holders should be produced the same for their perusal.
§ Any casual consultation between the stake holders can be done through telephone or e-mail, unless they do not require any documentation.
§ Communication between the stake holders resulting in the change in the project process should have a written authorization from the Project Manager and in such cases Project Manager should always be kept in loop.
§ The Project team will attend the project Kick-off meeting. Where in a detailed study of the Report would be done. This will be followed by a brain storming session to come up with the Project Scope, Scheduling and Costing.
§ Team will attend the Weekly Progress Meeting chaired by the Project Manager where in a stock of the Project progress will be taken, a weekly status report is produced along with the updated budget report, issues in the project team will be discussed and if required necessary documentation will be done.
§ Any feedbacks or suggestions from the project team will be left to the open discussion and with the proper evaluation, the feedbacks will be considered and the necessary documentation will be done.
§ Any resource requirement especially the Human Resource, will be taken care by the Project Manager in consultation with the Human Resource Department and the same will be documented through e-mail or on a Hard Copy.
Escalation Mechanism
Every Project related issues will be resolved by the onsite coordinator after discussing with the project manager.If a reasonable reply is not attained from each side, problems will be escalated as per the predefined escalation ladder shown below
The Below tables provide the levels of people in stakeholders to whom issues may be escalated..
Escalation Mechanism from BlueSky
Reason | Whom to Escalate |
1. Show Stopper | Delivery Manager |
2. Software related issues (cost center) | Project Leader |
3. Quality related Issues | Quality Assurance Manager |
4. Communication related issues | Project Manager |
Escalation mechanism from Basket Case
Reason | Whom to Escalate |
1. Expected deliverable not on time (When it occurs second time) | Project Leader |
2. Expected deliverable not on time (When it occurs third time) | Project Manager |
3. Expected deliverable not on time (When it occurs more than three times) | Delivery Manager |
Project Cost Management Plan
Cost Estimates of Resources
Resource Name | Resource Type | Units | Standard Rate | Cost/Use |
Project Manager | Work | 1 | $1,500.00/day | $0.00 |
Software Consultant | Work | 1 | $1,200.00/day | $0.00 |
Software Engineer | Work | 3 | $1,000.00/day | $0.00 |
Desktop Computer Support Personal | Work | 2 | $600.00/day | $0.00 |
Network Engineer | Work | 2 | $800.00/day | $0.00 |
Technical Writer | Work | 1 | $800.00/day | $0.00 |
Hardware Consultant | Work | 1 | $1,200.00/day | $0.00 |
Trainer | Work | 1 | $1,000.00/day | $0.00 |
Software Team Leader | Work | 1 | $1,200.00/day | $0.00 |
Hardware Team Lead | Work | 1 | $1,200.00/day | $0.00 |
Data Entry Operator | Work | 1 | $600.00/day | $0.00 |
Cabling Material (Smith Cables) | Material | 1 | $0.00 | $4,000.00 |
Cabling Contractor (Smith Cables) | Material | 1 | $0.00 | $4,000.00 |
Structural Contractor | Material | 1 | $0.00 | $4,000.00 |
Bluesky Software | Material | 1 | $0.00 | $200,000.00 |
Bluesky AMC | Material | 1 | $0.00 | $20,000.00 |
Oracle Software | Material | 1 | $0.00 | $25,230.00 |
Computer Hardware | Material | 1 | $0.00 | $174,915.00 |
UPS | Material | 1 | $0.00 | $6,300.00 |
Network Hardware | Material | 1 | $0.00 | $4,700.00 |
BlueSky uses GSOP (Global Standard Operating Procedure) for each and every phase of the project for the quality management. Every single document from every team should adhere to the GSOP. The documents can be uploaded in the docbase after the approval from the quality assurance team. If a document fails the GSOP, the appropriate individual will be notified by the QA team for changes or rework. Once the rework/changes are completed it will be again reviewed by the QA team and after final approval it will be uploaded in the docbase.
Risk Management is one of the challenges of the Project and requires a lot of fore sightedness and brain storming among the Stake Holders. The Risks that may arise during the course of the project is identified and tabulated according to the Priority along with the Mitigation Plan. The identified risks are prioritized based on an Excel based tool.
Low Probability Risks
Risk Type | Risk Description | Management Strategy |
1.Staff | The staffs are not familiar with the system or not good at operating the system | Train the staff before they start working, and teach them both the basic and advanced operations of system. |
Medium Probability Risks
Risk Type | Risk Description | Management Strategy |
1. Software Version | There is an increased vulnerability to incompatibilities in installed software versions. Thus modifications may cause inconsistent operating results. | Ensure that systems are properly tested and approved and that modifications are properly implemented. Determine that adequate version control procedures are properly implemented. |
2. Software Vulnerability | Data lost due to the unexpected reasons. Such as power cut, virus, etc. | Determine that the database management system has adequate recovery capabilities. |
3. Project members | Members complete their tasks on time, but being unable to satisfy the requirement. | Members should analyze task requirement carefully and ask project manager for more detail if there is anything unclear. Should the project manager have any inquiries, ask the project sponsor. Do not start any tasks before understand them clearly. |
High Probability Risks
Risk Type | Risk Description | Management Strategy |
1. Resource | Limited resources such as experienced programmer, consultant, engineer, money, etc. | Arrange the necessary resources before starting the project. Inform the stakeholder in case of inadequate resources. |
Very High Probability Risks
Risk Type | Risk Description | Management Strategy |
1. Finance | Due to some reasons, project requires more money, and cost overruns. | Monitor cost performance, record the cost and plan the resource. All cost including direct and indirect cost should be estimated. If the cost overruns, inform the change to the stakeholder. |
Procurement Planning
The procurement of the materials required for the IT infrastructure will be decided by the Project Manager and the Stake holders. Initially the Project manager will issue an RFP to some of the selected vendors, mentioning the requirements and the terms and conditions which will include conditions on delivery and support. Once the proposal from all vendors is received the Project Manager will decide on the proposal and the contract will be awarded to the best offer. All the hardware will be delivered to the basket case site and the IT officer will be the custodian of it.
The details on the procurement are as below,
Products | Procurement Method | Quantity | Required Delivery Date | Delivery Location |
Desktops | Fixed Price | 4 | 09-09-2005 | Basket Case Office |
6 | 09-09-2005 | Warehouse | ||
2 | 09-09-2005 | Factory | ||
Printers | Fixed Price | 2 Work group 1 Personal | 09-09-2005 | Basket Case Office |
1 Workgroup 1 Personal | 09-09-2005 | Warehouse | ||
1 Small laser printer | 09-09-2005 | Factory | ||
Laptops | Fixed Price | 6 | 09-09-2005 | Basket Case Office |
U P S | Fixed Price | 1 | 28-08-2005 | Basket Case Office |
Networking equipments | Fixed Price | 29-08-2005 | Basket Case Office | |
File, Email & Print server | Fixed Price | 1 | 09-09-2005 | Basket Case Office |
Database Server | Fixed Price | 1 | 09-09-2005 | Basket Case Office |
Application Server | Fixed Price | 1 | 09-09-2005 | Basket Case Office |
The software procurement will be done directly on the Fixed Price and terms basis. This will cover the purchase of the BlueSky package, Oracle database, and Office suite. The procurement will be done by the Project Manager himself.
Cabling
Total cabling installation work has been outsourced to Smiths Cables. They work on a cost plus fixed fee contract. Procurement of cables will be done from Smiths Cables.
Robert & Son have been assigned the work regarding the construction of the server room. The builder has inturn sub-contracted the electrician and locksmith. This will include air conditioning work required for the server room as well.
PROJECT EXECUTION
Initially a change request is logged into the system and then the impact analysis is done along with the risk assessment. Based on the impact the request is sub divided into minor and major changes where it needs the approval from the principal system specialist where the implementation/schedule date and time is produced. The Approval is based on the rollback script say in case of the updates in an oracle database. Once the rollback log is reviewed and approved the commit script is executed and the appropriate changes will be made.
Any changes occurring during the course of the project is tracked through Chameleon change control software. This helps in making sure that each change is tracked from start to the end and each change will have an owner who is responsible for it. This tracking of changes will help the finance team to bill Basket Case.
The Below figure explains how the change takes place in our system with the help of Chameleon Change control
The BlueSky team will use the change request process for any enhancements or bug fixes, or for changes to deliverables that have been approved by Client. The Below table indicated helps to log and monitor changes during the lifecycle of the project.
Change Control number | |
Change definition | |
Project Impact a. Agenda b. Attempt c. Price | |
Change Status | |
Requested Date | |
Approval/Rejected Date | |
Delivery Date | |
Date Finished | |
Comments | |
Signatures | |
Project Manager | Stake Holder |
Name | Name |
Signature & Date | Signature & Date |
BlueSky will be responsible for tracking and measuring all the relevant SLAs during the execution of the project. SLA data will be tracked on monthly basis. The cumulative SLA score will then be calculated every quarter to assess SLA adherence and determine the amount of penalty or bonus to be applied. INet a tool developed by EDS systems will be used for SLA management of issues.
Every three months, we will sit with our client together and review the SLA trends over the past quarter and, if necessary, changes in SLA parameters, measures and targets will be incorporated. BlueSky or Basket Case initiates a review exercise even before each quarter if necessary. The below diagram depicts the Basket Case SLA governance framework.
There is a weight age and priority for each SLA requests based on which the priority is marked as Low,Medium,High,Urgent,Ctirical.
§ Root cause analysis will be perfomed to identify the cause.
§ Detailed documentation for with the clear action plan will be created and shared with the clients.
If root cause analysis reveals a factor outside BlueSky's control as the cause, then the particular SLA Measure would be considered to have been met, after discussing the same with Client management in appropriate forum.
In the project we have used, Waterfall Model. The waterfall model is a Project Development Model first proposed in 1970 by W. W. Royce, in which development is seen as flowing steadily through the phases. The Spiral model is also incorporated if in case any change results mid way through the project.
Advantages
§ Good progress tracking due to clear development stages.
§ Milestones and deliverables can be clearly identified.
§ Project Management and control is facilitated by the need to complete each stage before moving to the next.
§ Inflexible partitioning of the project into distinct stages makes it difficult to respond to changing customer requirements.
§ Estimating time and costs is difficult for each stage.
Schedule Control
§ As discussed in the earlier section Project Scope change results in the Schedule change as well. Apart from this there are other factors that may force to change the Project Schedule.
Operational Change
§ Operational change could arise due to the technical factors. Any operational change will be dealt by the Project Manager and the Respective Team Lead (Software technical issues will be dealt by the Software team Lead and the Project Manager). Project Manager will be responsible for assessment, approval, implementation and acceptance of operational changes.
Contract Changes
§ The Stake holders have the right to change the proposal from the draft schedule, provided the changes does not breach the law or they do not have the technical and operational capability to handle the operational changes or accidents (emergency changes). The same holds good for the External contractors.
If a change request is issued by the external contractor, the Project Manager will undertake Impact Assessment. The impact assessment will comprehensively set out the details of the proposed change including: the details (and technical specifications of the change); the impact that the change will have on the performance and achievement. The Impact Assessment also includes a plan that details how the changes are implemented and a new timetable and budget estimate.
Cost Control
§ Cost being one of the major components of the Project, any change in the cost of the project will be given highest priority.
§ Any change in the cost (increase) during the course of the project will be discussed between the Stake holders and the Project Manager before it can be put forth of the Project Sponsor.
§ Depending on the % increase in the cost of the project from the estimated cost, a balancing act will be undertaken between time and cost but the Quality will not be compromised.
§ All the changes undertaken as a result of the cost change control plan will be documented and will be signed by the Project Sponsor and the Stake holders.
Quality Control
Audit is a thorough, systematic and independent examination carried out against defined criteria to determine whether:
§ Defined organization processes are adhered to.
§ Documentation of the project is maintained properly.
§ Change control mechanism is properly followed.
Scope Control
§ The Proposed project plan and all the documents related to the same are clearly verified and accepted by the Project Sponsor (Basket Case) and the Project contractor (BlueSky).
§ Any minor change in the scope of the project which does not result in the change of the project schedule, cost and time can be undertaken by the mutual agreement between the Project Sponsor and the Project Manager. Any other changes will be undertaken after a detailed brainstorming between the Sponsor and Project Stake Holders along with the Change Request form. All the documents (Change Request form) must be signed by the Stake holders. Only on consensus from the Stake holders the Project Manager will consider the effect of the scope change and re-evaluate the project with the required changes in the Project Schedule, Resource requirement, Costing, Human Resource requirement, Technical changes and Project completion Time. The final document should be signed by the Project Sponsor and the Project Manager before the changes can be implemented.
Risk Monitoring and Control is essential in every IT project, it extends to:
§ Continuously monitor for risks in the project and to predict future pitfalls
§ To evaluate if an identified risk has occurred or on the verge of occurrence
§ Check for risk mitigation strategy and put in place processes
§ Conduct periodic assessment of risks and check for risks that can occur
The risk team members are responsible for monitoring risk and to predict future risks. They need to update the steering committee on a regular basis of the status. During the meeting, all the identified risks will be reviewed for the likelihood of occurrence. Adequate measures should be planned in case of high risk cases. The frequency will be dependent upon the risk status and risk priority, as described below;-
Risk Status | Criteria/Frequency/Venue | Purpose |
---|---|---|
Received Pending Analysis | If the risks in this status are more than three days, will be reviewed on the team meeting with sponsor. | Assure Risks are being assigned promptly |
In Analysis | Risks will be reviewed with the project sponsor during the weekly meeting. | Ensure appropriate members and priority are assigned to analysis |
PM Review | Risks with status will be discussed in the weekly meeting with the project sponsor. | Create agreement with Sponsor on recommended actions |
Sponsor Review | Risks with status will be discussed in the weekly meeting with the project sponsor. | Achieve timely approval to implement recommendations |
Active - Priority 1 Risks | Reviewed with the Risk Owner and sponsor at an interval determined by the Project Manager and Sponsor from 1 to 30 days | Ensure that priority risks are closely monitored |
Active - Priority 2 & 3 Risks | Reviewed with the Risk Owner and Project Manager at an interval specified by the Project Manager from 1 to 90 days | Assure that all active risks are monitored for changes. |
Event Occurred | Project Sponsor will be notified with the risk event and updated on a weekly basis until the risk is raised as a change or incident management | Ensure prompt communication of risks that have occurred and active management of risk events. |
Closed | Reviewed as part of project closure | Identify lessons learned to improve future risk planning |
The results of each review will be entered on the Risk Review Record to provide history of the review.
Final Customer Acceptance
Before the project was deployed in the live environment, the stakeholders and the business users tested the system and the application was put on dry run. The stakeholders verified for the defined requirements and comments on changes to be made were documented in the change request system. The requested changes are planned to be deployed in the future maintenance release.
Final Project Performance
The Overall Project Performance was good in terms of the requirements implementation and the actual downtime period per month was much lesser compared to the expected downtime, the performance of the application was good where its been tested with huge user population.
Customer Satisfaction Survey
There are a few factors to be done in the customer Satisfaction survey,
The best time to conduct a customer satisfaction survey is when the experience is fresh in their minds.
* How satisfied are you with the purchase you made (of a product or service)
* How satisfied are you with the service you received?
* How satisfied are you with our company overall?
* How likely are you to buy from us again?
* How likely are you to recommend our product/service to others?
* How likely are you to recommend our company to others?
* We need to compile the answers from different customers
* We must act on the information we get from the customers through the survey.
* We need to fix the things the customers have complained about. We need to investigate their suggestions.
* We need to improve our company and product in those areas the mean the most to the most of our customers.
* Most importantly we need to give them feedback that their answers were appreciated and are being acted upon.
Closure Meeting with the Customer
§ Discuss the contents of the draft report
§ Clear up any anomalies or misunderstanding that may have arisen during the review
§ Discuss and provisionally agree recommendations, actions to be undertaken, officer(s) responsible and implementation dates
Post Implementation Review
There are three purposes for a Post-Implementation Review:
§ To ascertain the degree of success from the project, in particular, the extent to which it met its objectives, delivered planned levels of benefit, and addressed the specific requirements as originally defined.
§ To examine the efficacy of all elements of the working business solution to see if further improvements can be made to optimize the benefit delivered.
§ To learn lessons from this project, lessons which can be used by the team members and by the organization to improve future project work and solutions.
In some cases, the first of these objectives can be a contractual issue. Where that is the case, it may be safer to run separate reviews - one focused on contractual compliance and the other seeking to derive further benefit from a no-blame review.
The Project implementation is done with the below template and the findings and recommendations was presented to:
§ The solution's business owners
§ The leading participants in the project
§ Other parties who may be concerned with the results
Specific actions should be proposed to address any further work that is recommended. This might be handled in several different ways, for example:
§ as routine support and maintenance,
§ as remedial work to be performed by the original project team,
§ for line management to address through user education and procedures etc,
§ as further phases of development involving new projects.
1. Benefits Delivery
Exceeded | Met | Minor Shortfall | Major Shortfall | |
---|---|---|---|---|
The project met ROI and NPV targets? | Yes | |||
The project met internal customer requirements? | Yes | |||
The project met external customer requirements? | yes |
Above satisfactory | Appropriate | Below satisfactory | Not Appropriate or missing | |
---|---|---|---|---|
Were the deliverables clear? | Yes | |||
Were scope changes managed well? | Yes |
3. Schedule
Planned Completion Date | Actual Completion Date | ||||
Above satisfactory | Appropriate | Below satisfactory | Not Appropriate or missing | ||
Were activities clearly defined? | Yes | ||||
Was the schedule realistic? | Yes | ||||
Was the schedule tracked and monitored? | Yes |
Estimated Budget | Actual Budget | ||
Capital | 5m AUD | Capital | 5m AUD |
Expense | 3m AUD | Expense | 4m AUD |
Total Profit | 2m AUD | Total | 1m AUD |
Above satisfactory | Appropriate | Below satisfactory | Not Appropriate or missing | |
---|---|---|---|---|
Was an appropriate level of quality specified? | Yes | |||
Was the required level of quality met? | Yes | |||
Was the quality plan appropriate? | Yes |
Above satisfactory | Appropriate | Below satisfactory | Not Appropriate or missing | |
---|---|---|---|---|
Was there an agreed communication plan? | Yes | |||
Was there open and appropriate communication within the project team? | Yes | |||
Was there open and appropriate communication with the programme manager? | Yes | |||
Was there open and appropriate communication with the project sponsors? | Yes | |||
Was there open and appropriate communication with the customers? | Yes |
Above satisfactory | Appropriate | Below satisfactory | Not Appropriate or missing | |
---|---|---|---|---|
Were roles and responsibilities clear? | Yes | |||
Were there sufficient resources available? | Yes |
Above satisfactory | Appropriate | Below satisfactory | Not Appropriate or missing | |
---|---|---|---|---|
Was there an appropriate risk management plan? | Yes | |||
Were risks identified and mitigation strategies defined? | Yes | |||
Was any qualitative risk analysis undertaken? | Yes | |||
Was any quantitative risk analysis undertaken? | Yes | |||
Were resulting issues managed well? | Yes | |||
Were all outstanding issues at the end of the project moved to BAU or another project? | Yes |
Above satisfactory | Appropriate | Below satisfactory | Not Appropriate or missing | |
---|---|---|---|---|
Was there a procurement management plan? | Yes | |||
Was “make or buy” analysed? | Yes | |||
Were sellers evaluated appropriately? | Yes | |||
Were appropriate contracts made? | Yes |
Lessons Learnt, top three successes and failures
With the above post implementation review the top 3 successes are
§ Phase based approach instead of big bang approach of ERP Package is a huge success because of its steadiness.
§ Blue Sky ERP Package was best suited for ‘The Basket Case' and the customization was minimal which saved a huge time and capital.
§ After the implementation of Bluesky ERP package the efficiency of order placement increased from 5 minute/order to 1 minute/order.
Top 3 Failures
§ Training costs increased as the new resources walked into the project because the attrition rate was high as we went with Phase based approach.
§ Retail chain department's participation is very less which took a long time for us to understand their system and integrate.
§ Scope Creep because of poor communication between parties.
Archiving Project Documents
§ All Project related documents with every environments such as development, training, validation and production is stored in a docbase under documentum.
§ Only the employees working with ‘The Basket Case ‘Bluesky' project is/will be assigned access to the project documents with appropriate access level. Especially when it comes to the production related documents it is accessed only by the members who work with the maintenance and support project and the project management related documents will be accessed only by the Senior management.
Production related documents path | Ausprd31prdblueskybasketcase |
Development related documents path | Ausdev31devblueskybasketcase |
Validation related documents path | Ausval31valblueskybasketcase |
Training related documents path | Austrntrnblueskybasketcase |
·Schwalbe, Kathy.ThirdEdition, Information Technology Project Management,Cambridge, M.A.: Course Technology - Thomson Learning.
·Olson, David L. Second Edition, Information Systems Project Management, McGraw-Hill/Irwin.
·Tatnall, Arthur. First Edition, A Guide to Microsoft Project, Daca Publishing.
·https://en.wikipedia.org/wiki/Main_Page
·https://en.wikipedia.org/wiki/Waterfall_model
Appendix A
Bluesky implementation for basket case. (2017, Jun 26).
Retrieved November 21, 2024 , from
https://studydriver.com/bluesky-implementation-for-basket-case/
A professional writer will make a clear, mistake-free paper for you!
Get help with your assignmentPlease check your inbox
Hi!
I'm Amy :)
I can help you save hours on your homework. Let's start by finding a writer.
Find Writer